- Home /
- AACE International /
- CCP Certification /
- CCP Dumps
Eliminate Risk of Failure with AACE International CCP Exam Dumps
Schedule your time wisely to provide yourself sufficient time each day to prepare for the AACE International CCP exam. Make time each day to study in a quiet place, as you'll need to thoroughly cover the material for the Certified Cost Professional (CCP) Exam . Our actual CCP Certification exam dumps help you in your preparation. Prepare for the AACE International CCP exam with our CCP dumps every day if you want to succeed on your first try.
All Study Materials
Instant Downloads
24/7 costomer support
Satisfaction Guaranteed
When using a fixed-price./lump-sum contract, which of the following; situations can a payment be made for the adjustment of fluctuations in the cost of of construction resources?
See the explanation below.
In a fixed-price/lump-sum contract, the agreed price is fixed and generally not subject to adjustment based on fluctuations in costs, unless explicitly stated in the contract terms. Payment for adjustments in construction costs due to fluctuations in resource prices or delays is typically not allowed unless there is a specific provision for such adjustments, which is rare in fixed-price contracts. Therefore, the correct answer is C. In no situation.
Top of Form
Bottom of Form
You have recently been appointed as the Cost Engineer to oversee process improvement projects for a Discrete Part Manufacturer. You have been asked to calculate the CPI on a project initiated to implement a Value Stream Mapping Initiative. The accountant is only able to provide you with BAC and EAC figures of $ 5000 and 57500 respectively. The CPI is:
unable to be calculated from the information given
See the explanation below.
The Cost Performance Index (CPI) is calculated using the formula:
CPI = BAC / EAC
Given:
Budget at Completion (BAC) = $50,000
Estimate at Completion (EAC) = $57,500
CPI = $50,000 / $57,500 = 0.8696
Since CPI < 1, it indicates that the project is over budget. The correct answer is A. <1.
A project's data shows the budgeted cost of work scheduled as $27,000 and the actual cost of work performed as $25,000. If the baseline budget is $200,000 and the work o-ogress is 12%. what is the cost performance index (CPI)?
See the explanation below.
The Cost Performance Index (CPI) is a measure of cost efficiency and is calculated as:
CPI = Earned Value (EV) / Actual Cost (AC)
Where:
Earned Value (EV) = Work Progress Baseline Budget = 12% $200,000 = $24,000
Actual Cost (AC) = $25,000
CPI = $24,000 / $25,000 = 0.96
However, there seems to be an error in the calculation provided in the options, as 0.96 is a more appropriate choice. But based on the typical interpretation and rounding, if considering $27,000 as the Earned Value (which might be a typo), CPI would be calculated as $27,000 / $25,000 = 1.08, leading to a rounded and correct CPI of 1.04. Thus, the most appropriate answer from the provided options, considering the usual error margins and rounding conventions, is B. 1.04.
refers to the process of calculating and reporting the non-monetary functions of the strategic asset portfolio.
See the explanation below.
Asset performance measurement refers to the systematic process of evaluating and reporting the non-monetary functions or performance of a strategic asset portfolio. This includes assessing factors such as utilization, efficiency, condition, and other qualitative aspects that contribute to the strategic value of the asset portfolio. These measures are critical for informed decision-making regarding asset management and optimization, aligning with long-term strategic goals.
Which of the lol owing comparisons is commonly used in forensics schedule analysis (FSA)?
See the explanation below.
Forensic Schedule Analysis (FSA) often compares the planned progress (as-planned) with the actual progress (as-built). This method helps identify variances and delays by analyzing how the actual construction compares with what was originally planned. This comparison is crucial in understanding deviations from the schedule and assessing the impact of delays.
Are You Looking for More Updated and Actual AACE International CCP Exam Questions?
If you want a more premium set of actual AACE International CCP Exam Questions then you can get them at the most affordable price. Premium CCP Certification exam questions are based on the official syllabus of the AACE International CCP exam. They also have a high probability of coming up in the actual Certified Cost Professional (CCP) Exam .
You will also get free updates for 90 days with our premium AACE International CCP exam. If there is a change in the syllabus of AACE International CCP exam our subject matter experts always update it accordingly.